City Park, two 220 kV hada change through acceptance
Polaris Power Online News: Correspondent Wang Yingchun Liu Ying Ling reported recently, Tongliao City Park, the power
company, two 220 kV substations and Hada Branch City 220 kV lines, the line works, successfully passed the Liaoning
Provincial Power Station Project Quality Supervision Center pre-shipment inspection and supervision of investment
income.
City Park, Hada 220 kilovolt power transmission project, since construction started in July 2008, the company is
Tongliao power grid from 2008 to 2009 an important part of the construction. City Park covers an area of 34,436.6 square
meters of total substation, with a total construction area of 707.88 square meters, the installation of a main
transformer of 180 MVA, 220 kV outlet 10 back, 66 kV outlet 10 back. The total area of 19,416.3 square meters Hada
substation, with a total construction area of 876.54 square meters, the installation of a 120 MVA main transformer, 220
kV outlet 6 back, 66 kV outlet 7 back, install a group of 10 MVA capacitors. In addition to substation works, this
section also the city line, the river Ha lines 220 kV transmission line project for the new supervisory inspection, the
total line length of 136 km.
These two projects are Tongliao power company grid from 2008 to 2009 an important part of the construction. Project is
completed, Tongliao City to meet the 220 kV grid ring N-1 requirements, the grid structure is more reasonable, supply
capacity and reliability will be greatly improved, for local economic development has great significance.